Thirty Years and $2 Trillion Into the F-35 Program, the Fleet Is Fully Mission-Capable About a Quarter of the Time

Six F-35Bs arrived at the Marine Corps carrying ballast where their radars should have been, because the new APG-85 was not available. They can fly. They cannot conduct combat training or missions. That is the F-35 program at thirty years and a life-cycle estimate above $2 trillion: a fleet that is fully mission-capable about a quarter of the time, a modernization package five years late, 110 aircraft delivered in 2024 with every one late by an average of 238 days, and an aircraft whose complete upgrade consumes all 32 kilowatts of cooling it has, against a forward requirement of 62 to 80.

Maj. Kristin “BEO” Wolfe demonstrates the capabilities of the F-35A Lighting II, a single seat, single engine, all-weather stealth multirole fighter aircraft, during a practice flight with the F-35 Demonstration Team at Hill Air Force Base, Utah Feb. 6, 2024. (U.S. Air Force photo by Senior Airman Jack Rodgers)
Maj. Kristin “BEO” Wolfe demonstrates the capabilities of the F-35A Lighting II, a single seat, single engine, all-weather stealth multirole fighter aircraft, during a practice flight with the F-35 Demonstration Team at Hill Air Force Base, Utah Feb. 6, 2024. (U.S. Air Force photo by Senior Airman Jack Rodgers)

Nearly 30 Years Into the F-35 Program, Three Problems Still Define Its $2 Trillion Future: The Joint Strike Fighter program began in November 1996. By July 31, 2026, it had been underway for almost 30 years. The Pentagon plans to buy 2,470 U.S. aircraft, and the Government Accountability Office estimates that acquisition and sustainment across the fleet’s 77-year life cycle will cost more than $2 trillion.

The F-35 has genuine strengths. Its low-observable design, sensor fusion, and networking give U.S. and allied forces a penetrating aircraft capable of finding targets and sharing data in heavily defended airspace. The Pentagon still has to keep enough jets ready and modernize them before the aircraft’s original hardware reaches its limits.

The latest readiness data provide the sharpest warning. GAO reported in June 2026 that the fleet-wide mission-capable rate fell from 67 percent in fiscal 2021 to 44 percent in fiscal 2025. The full mission-capable rate, measuring the share of time a jet was able to perform every assigned mission, fell from 38 percent to 25 percent.

As of July 31, 2026, three problems stand above the rest: a sustainment system that has not kept pace with fleet growth, a Block 4 modernization effort trapped by software and testing delays, and an engine-and-cooling architecture with almost no margin for the capabilities planned in the 2030s.

F-35 Readiness Fell as the U.S. Fleet Passed 800 Aircraft

The readiness decline does not trace to one defective component. Air Force officials cited newly accepted aircraft limited by software, scarce spare parts, and corrosion inspections and repairs. The result was a force in which the fleet was fully mission-capable only about one-quarter of the time during fiscal 2025, even as the U.S. inventory surpassed 800 aircraft.

The Joint Program Office now proposes a major sustainment reset through fiscal 2031. The plan requires $13.7 billion beyond previous projections, with more than $7 billion dependent on the industry delivering additional parts and materials. GAO found continuing capacity constraints for key items and projected that the services will face an annual sustainment gap above $1 billion by the mid-2030s.

Program Executive Officer Lt. Gen. Gregory Masiello told the Senate in June that the current support structure was built for 700 to 800 aircraft and now serves more than 1,300 accepted F-35s worldwide. That is the underlying readiness problem: procurement expanded faster than depots, repair capacity, spare inventories, and government access to technical data.

Masiello did not dispute GAO’s calculation, but said the Joint Program Office’s current figure placed mission-capable performance at 56 percent. That higher figure does not erase the five-year decline or the decision to launch a multibillion-dollar sustainment reset.

A U.S. Air Force F-35A Lightning II, assigned to the F-35A Lightning II Demonstration Team, performs precision aerial maneuvers during the Columbus Air Show at Rickenbacker Air National Guard Base, Columbus, Ohio, June 21, 2026. The F-35A Demonstration Team showcases the unique aerodynamic capabilities, advanced avionics, and combat readiness of the military's premier fifth-generation fighter to inspire the next generation of Airmen and demonstrate American air power. (U.S. Air National Guard photo by Airman 1st Class Samir Harris)

A U.S. Air Force F-35A Lightning II, assigned to the F-35A Lightning II Demonstration Team, performs precision aerial maneuvers during the Columbus Air Show at Rickenbacker Air National Guard Base, Columbus, Ohio, June 21, 2026. The F-35A Demonstration Team showcases the unique aerodynamic capabilities, advanced avionics, and combat readiness of the military’s premier fifth-generation fighter to inspire the next generation of Airmen and demonstrate American air power. (U.S. Air National Guard photo by Airman 1st Class Samir Harris)

An F-35A Lightning II pilot assigned to the 125th Fighter Wing conducts a preflight maintenance check at Jacksonville Air National Guard Base, Florida, April 15, 2026. Coordination between pilots and maintainers ensures aircraft are mission-ready to execute aerospace control and air defense missions under Air Combat Command. The 125th FW sustains readiness to support federal and state missions, including combat operations, humanitarian assistance, and disaster response. (U.S. Air National Guard photo by Staff Sgt. N.W. Huertas)

An F-35A Lightning II pilot assigned to the 125th Fighter Wing conducts a preflight maintenance check at Jacksonville Air National Guard Base, Florida, April 15, 2026. Coordination between pilots and maintainers ensures aircraft are mission-ready to execute aerospace control and air defense missions under Air Combat Command. The 125th FW sustains readiness to support federal and state missions, including combat operations, humanitarian assistance, and disaster response. (U.S. Air National Guard photo by Staff Sgt. N.W. Huertas)

An F-35A Lightning II from the 388th Fighter Wing on display on a taxiway during Feria Internacional del Aire y del Espacio (FIDAE) in Santiago, Chile, April 11, 2026. The F-35A Lightning II is a fifth-generation multirole fighter designed for air superiority and precision strike missions. (U.S. Air Force photo by Staff Sgt. Derek Gutierrez)

An F-35A Lightning II from the 388th Fighter Wing on display on a taxiway during Feria Internacional del Aire y del Espacio (FIDAE) in Santiago, Chile, April 11, 2026. The F-35A Lightning II is a fifth-generation multirole fighter designed for air superiority and precision strike missions. (U.S. Air Force photo by Staff Sgt. Derek Gutierrez)

Combat units often post stronger readiness when parts, maintainers, and contractor support are concentrated for a deployment. A global fleet cannot treat every squadron as a surge operation. Routine readiness has to cover training units, test squadrons, home stations, and deployed forces without stripping one group to support another.

Block 4 Is Five Years Late and Still Waiting on Stable Software

Block 4 is intended to add weapons, electronic warfare improvements, radar enhancements, and communications upgrades needed against changing threats. GAO placed the effort at $16.5 billion as of 2021, more than 50 percent above its original baseline. The Pentagon has since reduced the package and moved completion to 2031 at the earliest, five years beyond the original schedule.

Technology Refresh 3, or TR-3, is the $1.9 billion computing and memory foundation for much of Block 4. Its hardware and software delays drove late production deliveries. Lockheed Martin delivered 110 aircraft in 2024, and every one arrived late by an average of 238 days.

The software problem continued after deliveries resumed. The Pentagon’s operational-test office found that the latest TR-3 software was unsuitable for dedicated testing, while the final software planned for older TR-2 aircraft was largely unusable for much of fiscal 2025 because of instability, missing capability, and newly discovered defects. No new combat capability was fielded during that fiscal year.

Masiello told senators on June 23 that 22 original Block 4 requirements had been fielded, including seven in the previous software release, with six more planned for summer 2026. The hearing also showed the limiting factor behind the software delays: integration and test capacity has not kept pace with the volume and complexity of code. The operational-test force still lacks enough properly configured aircraft and simulation equipment to test representative formations on schedule.

The hardware delay is also reaching finished aircraft. The Marine Corps accepted six F-35Bs with ballast instead of radars because the new APG-85 was unavailable. Those jets support basic flying but cannot conduct combat training or missions until their radars are installed.

The F-35 Is Running Out of Power and Cooling Margin

New processors, radars, and electronic-warfare systems draw electricity and produce heat. During the June Senate hearing, Masiello said the complete Block 4 configuration consumes the aircraft’s available 32 kilowatts of cooling capacity, leaving no margin. The program’s forward requirement is between 62 and 80 kilowatts.

The shortfall has been known since 2008. The current engine has to work harder to extract power and reject heat, reducing component life. GAO estimated that the resulting wear has added $38 billion to projected life-cycle costs. The limitation also pushes some capabilities beyond the reduced Block 4 package because the aircraft lacks the power and cooling to support them.

The Pentagon chose an Engine Core Upgrade for the existing F135 rather than a new adaptive engine. The upgrade is meant to restore engine life and provide additional power, but it supplies only part of the cooling increase. A separate power-and-thermal-management upgrade must handle the greater demand and later mission systems, an issue also driving the aircraft’s modernization bill.

The Engine Core Upgrade is scheduled to enter critical design review in August 2026, followed by ground testing in late 2027 and flight testing around 2030. Production is expected in 2031. GAO’s current schedule does not begin production of the larger power-and-thermal-management upgrade until 2033.

About the Author: Harry J. Kazianis

Harry J. Kazianis (@Grecianformula) was the former Senior Director of National Security Affairs at the Center for the National Interest (CFTNI), a foreign policy think tank founded by Richard Nixon based in Washington, DC. Harry has over a decade of experience in think tanks and national security publishing. His ideas have been published in the NY Times, The Washington Post, The Wall Street Journal, CNN, and many other outlets worldwide. He has held positions at CSIS, the Heritage Foundation, the University of Nottingham, and several other institutions related to national security research and studies. He is the former Executive Editor of the National Interest and the Diplomat. He holds a Master’s degree focusing on international affairs from Harvard University.

Written By

Harry J. Kazianis (@Grecianformula) is Editor-In-Chief of 19FortyFive and National Security Journal. Kazianis recently served as Senior Director of National Security Affairs at the Center for the National Interest. He also served as Executive Editor of its publishing arm, The National Interest. Kazianis has held various roles at The National Interest, including Senior Editor and Managing Editor over the last decade. Harry is a recognized expert on national security issues involving North & South Korea, China, the Asia-Pacific, Europe, and general U.S. foreign policy and national security challenges. Past Experience Kazianis previously served as part of the foreign policy team for the 2016 presidential campaign of Senator Ted Cruz. Kazianis also managed the foreign policy communications efforts of the Heritage Foundation, served as Editor-In-Chief of the Tokyo-based The Diplomat magazine, Editor of RealClearDefense, and as a WSD-Handa Fellow at the Center for Strategic and International Studies (CSIS): PACNET. Kazianis has also held foreign policy fellowships at the Potomac Foundation and the University of Nottingham. Kazianis is the author of the book The Tao of A2/AD, an exploration of China’s military capabilities in the Asia-Pacific region. He has also authored several reports on U.S. military strategy in the Asia-Pacific as well as edited and co-authored a recent report on U.S.-Japan-Vietnam trilateral cooperation. Kazianis has provided expert commentary, over 900 op-eds, and analysis for many outlets, including The Telegraph, The Wall Street Journal, Yonhap, The New York Times, Hankyoreh, The Washington Post, MSNBC, 1945, Fox News, Fox Business, CNN, USA Today, CNBC, Politico, The Financial Times, NBC, Slate, Reuters, AP, The Washington Examiner, The Washington Times, RollCall, RealClearPolitics, LA Times, Newsmax, BBC, Foreign Policy, The Hill, Fortune, Forbes, DefenseOne, Newsweek, NPR, Popular Mechanics, VOA, Yahoo News, National Security Journal and many others.