2 Days at Sea Cost Royal Navy Aircraft Carrier HMS Prince of Wales 328 Days in Dock. Failed Coupling on Her Starboard Propeller Shaft Was the Problem

Two days after leaving Portsmouth on August 27, 2022, the 65,000-ton aircraft carrier HMS Prince of Wales was anchored off the Isle of Wight with a failed coupling on her starboard shaft, a 33-ton propeller damaged and a North American deployment canceled. The investigation found the shaft had been misaligned during construction, the problem had been reviewed, accepted and certified in 2019 with no restriction, and the port shaft was off too. The £25 million repair kept her at Rosyth until July 2023 and left the Navy holding the bill, because a warranty would have cost more than the fix; her 40,000-mile 2025 Indo-Pacific deployment was the proof it worked.

Royal Navy Queen Elizabeth Aircraft Carrier Creative Commons Image
Royal Navy Queen Elizabeth Aircraft Carrier Creative Commons Image

Summary and Key Points: Harry J. Kazianis dissects the August 2022 shaft failure that disabled aircraft carrier HMS Prince of Wales two days out of Portsmouth: a coupling on the starboard shaft, misaligned during construction and certified in 2019 without restriction, failed off the Isle of Wight, damaging the 33-ton propeller, canceling WESTLANT 22’s F-35B trials, and costing £25 million and dry dock at Rosyth until July 21, 2023. Her 2025 Indo-Pacific deployment, 40,000 nautical miles, proved the repair.

Military History That No One Wants to Remember: The HMS Prince of Wales Aircraft Carrier Problems 

Queen Elizabeth-Class Aircraft Carrier HMS Prince of Wales

HMS Prince of Wales Aircraft Carrier Queen Elizabeth-Class Aircraft Carrier. Image Credit: Creative Commons.

HMS Prince of Wales sailed from Portsmouth on August 27, 2022, for a three-month deployment to North America. Within two days, Britain’s 65,000-tonne aircraft carrier was anchored off the Isle of Wight with a failed coupling on her starboard propeller shaft.

The mission was canceled, the ship returned to port, and repairs eventually cost about £25 million. Prince of Wales did not leave dry dock at Rosyth until July 21, 2023.

The official investigation found a more serious explanation than bad luck at sea.

The starboard shaft had been misaligned during construction, and key components had been installed incorrectly.

The Ministry of Defence identified one causal factor and numerous contributory and aggravating factors behind the defect. The coupling failure was the final event in a problem built into the ship before she entered Royal Navy service.

The inquiry also revealed how the problem persisted despite acceptance. The effect of the misalignment had been reviewed during construction, and the decision was made to proceed to sea trials with further monitoring.

Prince of Wales then sailed thousands of nautical miles while vibration readings remained within limits. She received the required naval and Lloyd’s Register certificates in 2019, with no restriction placed on the shafts and no continuing monitoring requirement transferred to the Navy.

Royal Navy. HMS Prince of Wales Aircraft Carrier.

Royal Navy HMS Prince of Wales Aircraft Carrier. Image Credit: Creative Commons.

HMS Prince of Wales Royal Navy

HMS Prince of Wales Royal Navy. Image Credit: Royal Navy.

After the starboard failure, engineers also found an alignment issue on the port shaft and repaired both sides.

Checks on HMS Queen Elizabeth found no comparable misalignment, leading the Ministry of Defence to reject the idea of a class-wide construction defect.

The public investigation did not identify every wrongly installed component or publish the alignment measurements, leaving the engineering details behind the failure only partly disclosed.

A Coupling Failure Disabled a 65,000-Tonne Aircraft Carrier

The Queen Elizabeth-class uses integrated electric propulsion.

Two Rolls-Royce MT30 gas-turbine alternators and four diesel generators produce electricity for ship systems and four large propulsion motors.

Those motors drive two long shafts and fixed-pitch propellers. Because each shaft runs through a large part of the hull, it is manufactured in sections.

The failed coupling joined the final two sections of the starboard shaft.

A shaft line has to remain aligned through its bearings, couplings, and supports while transferring enormous torque to the propeller. Misalignment creates loads the system was not intended to absorb.

Royal Navy divers found significant damage to the shaft and 33-tonne propeller, plus superficial damage to the rudder. The propeller was removed before Prince of Wales sailed north on one shaft for Rosyth, one of the few British docks large enough to take the carrier.

The HMS Prince of Wales (R09) aircraft carrier flight deck officer “shoots” an F-35B Lightning II short takeoff vertical landing (STOVL) variant fighter jet for a STO launch from a ski jump aboard the U.K.’s newest carrier Oct. 24, 2023. The 5th generation strike aircraft for Navy, Air Force, Marines, and allies is aboard to conduct developmental test phase 3 (DT-3) flight trials, which continue today. During the ship's deployment to the U.S. Eastern Seaboard for WESTLANT 2023, a Pax River F-35 Integrated Test Force (Pax ITF) team is working closely with the ship's company to conduct the sea trials that continue pushing the boundaries of carrier aviation. (Photo by Michael D. Jackson)

The HMS Prince of Wales (R09) aircraft carrier flight deck officer “shoots” an F-35B Lightning II short takeoff vertical landing (STOVL) variant fighter jet for a STO launch from a ski jump aboard the U.K.’s newest carrier Oct. 24, 2023. The 5th generation strike aircraft for Navy, Air Force, Marines, and allies is aboard to conduct developmental test phase 3 (DT-3) flight trials, which continue today. During the ship’s deployment to the U.S. Eastern Seaboard for WESTLANT 2023, a Pax River F-35 Integrated Test Force (Pax ITF) team is working closely with the ship’s company to conduct the sea trials that continue pushing the boundaries of carrier aviation. (Photo by Michael D. Jackson)

The breakdown carried extra reputational damage because the Prince of Wales had entered commission only in December 2019. The two-carrier construction program cost £6.4 billion. Between October 2020 and April 2021, the ship had already spent 193 days alongside while workers repaired flood damage. The 2022 shaft failure therefore looked less like an isolated early-service defect and more like another warning about the material state of Britain’s newest capital ship.

WESTLANT 22 Lost Its Most Important Flight Trials

The canceled deployment was not part of the routine port-visit schedule. WESTLANT 22 was intended to expand F-35B operations, test uncrewed aircraft, and refine how Britain’s two carriers would use new aviation technology. The task group planned to work with American and Canadian forces and visit New York, Halifax, and the Caribbean. HMS Queen Elizabeth crossed the Atlantic to assume some of the diplomatic and operational work, allowing the Royal Navy to meet its NATO commitments.

Queen Elizabeth could not duplicate the entire test program at short notice because the Prince of Wales carried specialized equipment for the developmental flying. The lost F-35 and drone work moved into 2023.

The Ministry of Defence later argued that the wider operational effect was limited because Prince of Wales had already been scheduled to spend much of 2023 alongside for flight-deck, communications, and combat-system upgrades.

Those upgrades were completed at Rosyth while both shafts were repaired.

The £25 Million Repair Raised a Liability Question

The Navy initially paid the repair bill from its own budget. Officials estimated the work at roughly £25 million and said responsibility had not yet been established. The complication was the contracting model.

Prince of Wales had been delivered by the Aircraft Carrier Alliance, a partnership in which the Ministry of Defence itself worked with BAE Systems, Babcock and Thales. Officials told Parliament that an extended warranty for a project of this scale would have cost far more than the repair.

That explanation protected the original procurement model but did not erase the central failure: a known alignment concern was deemed acceptable, passed trials, and became a major casualty three years after the vessel was accepted.

The episode now sits at the center of the debate over Prince of Wales’ availability record.

It also reinforced the case for keeping two carriers rather than placing Britain’s entire carrier-strike capability in one hull.

Two Carriers Limited the Damage but Did Not Remove It

Here, redundancy worked both ways. Queen Elizabeth covered part of the abandoned 2022 program.

In February 2024, Prince of Wales prepared in eight days and replaced her sister on a major NATO exercise after inspectors found a different problem with Queen Elizabeth’s starboard shaft coupling. The government said the second defect was not the same as the 2022 failure.

The exchange showed why the two-carrier force has operational value, even when each ship spends long periods in maintenance.

Prince of Wales also completed the work lost in 2022. Her 2023 American deployment expanded the F-35B operating envelope and tested uncrewed aircraft from the flight deck. She later led the 2025 carrier deployment to the Indo-Pacific, returning after eight months and more than 40,000 nautical miles.

That voyage provided the strongest evidence that the shaft repairs restored the ship rather than offered a temporary fix.

The repaired carrier then returned to high-readiness work in northern waters.

The 40,000-mile deployment had already tested the ship across three oceans.

On July 24, 2026, HMS Prince of Wales returned to Portsmouth after three months leading Operation Firecrest in the North Atlantic and Arctic.

About the Author: Harry J. Kazianis

Harry J. Kazianis (@Grecianformula) was the former Senior Director of National Security Affairs at the Center for the National Interest (CFTNI), a foreign policy think tank founded by Richard Nixon based in Washington, DC. Harry has over a decade of experience in think tanks and national security publishing. His ideas have been published in the NY Times, The Washington Post, The Wall Street Journal, CNN, and many other outlets worldwide. He has held positions at CSIS, the Heritage Foundation, the University of Nottingham, and several other institutions related to national security research and studies. He is the former Executive Editor of the National Interest and the Diplomat. He holds a Master’s degree focusing on international affairs from Harvard University.

Written By

Harry J. Kazianis (@Grecianformula) is Editor-In-Chief of 19FortyFive and National Security Journal. Kazianis recently served as Senior Director of National Security Affairs at the Center for the National Interest. He also served as Executive Editor of its publishing arm, The National Interest. Kazianis has held various roles at The National Interest, including Senior Editor and Managing Editor over the last decade. Harry is a recognized expert on national security issues involving North & South Korea, China, the Asia-Pacific, Europe, and general U.S. foreign policy and national security challenges. Past Experience Kazianis previously served as part of the foreign policy team for the 2016 presidential campaign of Senator Ted Cruz. Kazianis also managed the foreign policy communications efforts of the Heritage Foundation, served as Editor-In-Chief of the Tokyo-based The Diplomat magazine, Editor of RealClearDefense, and as a WSD-Handa Fellow at the Center for Strategic and International Studies (CSIS): PACNET. Kazianis has also held foreign policy fellowships at the Potomac Foundation and the University of Nottingham. Kazianis is the author of the book The Tao of A2/AD, an exploration of China’s military capabilities in the Asia-Pacific region. He has also authored several reports on U.S. military strategy in the Asia-Pacific as well as edited and co-authored a recent report on U.S.-Japan-Vietnam trilateral cooperation. Kazianis has provided expert commentary, over 900 op-eds, and analysis for many outlets, including The Telegraph, The Wall Street Journal, Yonhap, The New York Times, Hankyoreh, The Washington Post, MSNBC, 1945, Fox News, Fox Business, CNN, USA Today, CNBC, Politico, The Financial Times, NBC, Slate, Reuters, AP, The Washington Examiner, The Washington Times, RollCall, RealClearPolitics, LA Times, Newsmax, BBC, Foreign Policy, The Hill, Fortune, Forbes, DefenseOne, Newsweek, NPR, Popular Mechanics, VOA, Yahoo News, National Security Journal and many others.